SN
|
Blue book Item No./ Railway Board’s Letter No.
|
Year of sanction
|
Name of survey
|
State
|
Progress %
|
Present status
|
Target date of completion
|
(A): New Line Surveys
|
1
|
Sanctioned vide item no.26 of Blue book of 2012-13
|
2012-13
|
RETS for Construction of new line to extend linkage with Chittagong & Belonia to connect with Bangladesh Railway. (125 km)
|
Tripura (India) Chittagong (Bangladesh)
|
|
The survey being International, letter to ED/works has been sent on dtd. 24.08.12, 14.12.12 & 20.03.13 for sanctioning of 175.0 Lakhs for conducting survey works through RITES Ltd.
|
Not yet fixed
|
2
|
Railway Board’s Letter No. 2012/W-I/Genl./Surveys/Budget dtd. 19-07-2012
|
2012-13
|
RETS for Imphal to Moreh (90km)
|
Manipur
|
80%
|
Alignment approved. Field survey is in progress. As desired by CE/CON/VII, more alternative proposals are under verification.
|
June 2013
|
3
|
Sanctioned vide item no.19 of Blue Book of 2013-14
|
2013-14
|
RET survey for new line from Sairang to Hbichhuah rail link for port connectivity on Colodyne River. (266km)
|
Mizoram
|
15%
|
Survey estimate Sanctioned. NIT issued on 21-05-2013
|
March 2014
|
4
|
Sanctioned vied item no.20 of Blue Book of 2013-14
|
2013-14
|
RET survey for new line from Panisagar to Simanapur (80 km)
|
Tripura
|
15%
|
Survey estimate Sanctioned. NIT issued on 21-05-2013
|
Jan 2014
|
5
|
Sanctioned vied item no.20 of Blue Book of 2013-14
|
2013-14
|
RET survey for new line from Patharkandi to Kanmum (45km)
|
Assam & Mizoram
|
15%
|
Survey estimate Sanctioned. NIT issued on 21-05-2013
|
Feb 2014
|
(B): Updating Doubling Surveys
|
6
|
Railway Board’s Letter No. 2011/WI/NF/DL/New Mainaguri-New Coochbehar dt. 13.01.2012 and as per requirement of Operating Deptt.
|
2012-13
|
Updating of RET Survey for Doubling from New Mainaguri to Gumanihat (51.65km)
|
West Bengal
|
60%
|
Estimate is under finance vetting. Report under preparation.
|
June 2013
|
(C): Updating New Line Surveys
|
7
|
Railway Board’s Letter No. 2013/WI/Genl/survey/12-13
|
2012-13
|
Updating of PET Survey for construction of a Rail-cum-Road Bridge between Teznarayanpur-Sahibganj (12km)
|
Bihar
|
10%
|
Survey estimate is under process of approval.
|
December 2013
|