उपलब्धियां 2008-09
|
|
OUTLAY 2008 – 09:
|
1
|
New Lines
|
:
|
Rs.
|
697.72
|
Crores
|
2
|
Gauge Conversion
|
:
|
Rs.
|
737.94
|
Crores
|
3
|
Doubling
|
:
|
Rs.
|
38.86
|
Crores
|
4
|
Others
|
:
|
Rs.
|
45.56
|
Crores
|
|
Total
|
:
|
Rs.
|
1520.08
|
Crores
|
|
|
|
|
|
|
EXPENDITURE 2008 -09:
|
1
|
New Lines
|
:
|
Rs.
|
714.76
|
Crores
|
2
|
Gauge Conversion
|
:
|
Rs.
|
757.29
|
Crores
|
3
|
Doubling
|
:
|
Rs.
|
41.29
|
Crores
|
4
|
Others
|
:
|
Rs.
|
49.43
|
Crores
|
|
Total
|
:
|
Rs.
|
1562.77
|
Crores
|
|
|
|
|
|
|
MILESTONES:
|
|
Manu- Agartala (89kms) completed and commissioned on 05.10.08.
|
|
Katihar-Jogbani (108 Km) completed and commissioned on 04.06.08.
|
|
In Senchoa-Silghat (62 Km) , work completed and CRS sanction for opening of the section received
|
|
The work of augmentation of wagon maintenance facility in the sick line at New Guwahati
completed.
|
|
The work of coach bogie overhauling at Dibrugarh Workshop completed.
|
|
|