उपलब्धियां 2010-11
|
|
OUTLAY 2010 – 11:
|
1
|
New Lines
|
:
|
Rs.
|
1018.00
|
Crores
|
2
|
Gauge Conversion
|
:
|
Rs.
|
1087.97
|
Crores
|
3
|
Doubling
|
:
|
Rs.
|
39.00
|
Crores
|
4
|
Others
|
:
|
Rs.
|
18.24
|
Crores
|
|
Total
|
:
|
Rs.
|
2163.21
|
Crores
|
|
|
|
|
|
|
EXPENDITURE 2010 -11:
|
1
|
New Lines
|
:
|
Rs.
|
1056.08
|
Crores
|
2
|
Gauge Conversion
|
:
|
Rs.
|
1111.50
|
Crores
|
3
|
Doubling
|
:
|
Rs.
|
36.74
|
Crores
|
4
|
Others
|
:
|
Rs.
|
18.53
|
Crores
|
|
Total
|
:
|
Rs.
|
2222.85
|
Crores
|
|
|
|
|
|
|
MILESTONES:
|
|
Malda – Old Malda Doubling of track over Mahananda Bridge has been completed and commissioned on 25.06.2010
|
|
Under Patch Doubling in New Guwahati – Digaru section, 20 kms have been commissioned under Phase-I
|
|
In New Coochbehar – Golakganj Section (New Line): P. Way has been linked and engine rolled from both New Coochbehar and Golakganj ends.
|
|
Katihar – Manihari (24.4 km) section: Gauge Conversion is ready for CRS Inspection
|
|
Gauge Conversion in Aluabari – Siliguri Jn. section: Engine rolled in full section.
|
|
|