ACHIEVEMENT HIGHLIGHTS 2011 – 12
|
OUTLAY 2011-12:
|
1
|
New Lines
|
:
|
Rs.
|
1177.09
|
Crores
|
2
|
Gauge Conversion
|
:
|
Rs.
|
961.95
|
Crores
|
3
|
Doubling
|
:
|
Rs.
|
18.00
|
Crores
|
4
|
Others
|
:
|
Rs.
|
22.29
|
Crores
|
|
Total
|
:
|
Rs.
|
2179.33
|
Crores
|
|
|
|
|
|
|
EXPENDITURE 2011 -12:
|
1
|
New Lines
|
:
|
Rs.
|
1225.47
|
Crores
|
2
|
Gauge Conversion
|
:
|
Rs.
|
970.91
|
Crores
|
3
|
Doubling
|
:
|
Rs.
|
17.97
|
Crores
|
4
|
Others
|
:
|
Rs.
|
20.01
|
Crores
|
|
Total
|
:
|
Rs.
|
2234.36
|
Crores
|
MILESTONES:
Gauge Conversion in Aluabari – Siliguri Jn. section has been completed and commissioned.
Patch Doubling in New Guwahati – Digaru section has been completed and commissioned.
Patch Doubling in New Guwahati – Digaru section has been completed and commissioned.
Engine Rolled in the following sections:
- New Mal – Changrabandha on 07.02.2012
- Rangiya – Rangapara on 12.3.2012 & 17.3.2012
- Jiribam – Dholakhal on 22.03.2012