Achievement Highlights 2025-2026
RBG :2025-2026(Rupees in Crores)
|
1
|
New Lines
|
7642.13
|
|
2
|
Gauge Conversion
|
10.00
|
|
3
|
Doubling
|
1000.00
|
|
|
|
8652.13
|
EXPENDITURE : 2025-2026 (Rupees in Crores)
|
1
|
New Lines
|
6092.8956
|
|
2
|
Gauge Conversion
|
3.6889
|
|
3
|
Doubling
|
789.6221
|
|
|
|
6886.2066
|
Commissioning : 2025-2026
PROJECTS COMMISSIONED BASED ON CRS AUTHORISATION
|
NEW LINES
|
GAUGE CONVERSION
|
DOUBLING
|
TOTAL
KM
|
|
SN
|
SECTION
|
KM
|
CRS Authorization Date
|
SN
|
SECTION
|
KM
|
CRS Authorization Date
|
SN
|
SECTION
|
KM
|
CRS Inspection Date
|
|
1
|
Hortoki-Sairang
|
33.86
|
10/06/2025
|
|
Nil
|
|
|
|
Nil
|
|
|
|
| 2 |
Rahamatpur - Pawakhali
|
79.77
|
11/07/2025
|
|
|
|
|
|
|
|
|
|
|
|
Total Length =
|
113.63
|
|
|
|
|
|
|
|
|
|
|
Re Opening of train services in Vangaichunpao - Khongsang section (NEW LINES)
|
NEW LINES
|
GAUGE CONVERSION
|
DOUBLING
|
TOTAL
KM
|
|
SN
|
SECTION
|
KM
|
CRS Authorization Date
|
SN
|
SECTION
|
KM
|
CRS Authorization Date
|
SN
|
SECTION
|
KM
|
CRS Inspection Date
|
|
1
|
Vangaichunpao - Khongsang
|
43.3
|
29/01/2026
|
|
Nil
|
|
|
|
Nil
|
|
|
|
|
|
Total Length =
|
43.3
|
|
|
|
|
|
|
|
|
|
|
|