Achievement Highlights 2021-2022
OUTLAY :2021-2022(Rupees in Crores)
1
|
New Lines
|
4520.0016
|
2
|
Gauge Conversion
|
0.0005
|
3
|
Doubling
|
1205.0003
|
|
|
5725.0024
|
EXPENDITURE : 2021-2022 (Rupees in Crores)
1
|
New Lines
|
5103.67
|
2
|
Gauge Conversion
|
22.125
|
3
|
Doubling
|
1864.69
|
|
|
6990.49
|
Mile Stones:
Commissioning : 2021-2022
NEW LINES
|
GAUGE CONVERSION
|
DOUBLING
|
TOTAL
KM
|
SN
|
SECTION
|
KM
|
CRS Authorization Date
|
SN
|
SECTION
|
KM
|
CRS Authorization Date
|
SN
|
SECTION
|
KM
|
CRS Inspection Date
|
1
|
Dhansiri-Shokhuvi (NL)
|
16.2
|
29/10/2021
|
|
Nil
|
|
|
1
|
Jalpaiguri Road (Excl)-Y-Leg connection
|
4.928
|
30.06.2021
|
|
2 |
Bilasipara(Excl)-Abhayapuri (Excl)
|
47.728
|
18/12/2021
|
|
|
|
|
2
|
Betgara-Kolaigram (UP Line)
|
22.533
|
01/07/2021
|
|
|
|
|
|
|
|
|
|
3 |
Kolaigram to Gumanihat (DL) |
24.14 |
06/10/2021 |
|
|
|
|
|
|
|
|
|
4 |
Dharamtul-Kampur (Excl.) |
32.468 |
03/11/2021 |
|
|
|
|
|
|
|
|
|
5 |
Pancharatha-Dudhnai/DL |
28.143 |
27/02/2022 |
|
|
|
|
|
|
|
|
|
6 |
Jagiroad(Excl) to Dharamtul (Excl) |
18.66 |
14/03/2022 |
|
|
Total Length =
|
63.928
|
|
|
|
|
|
|
Total Length =
|
130.872
|
|
194.8
|
|