Achievement Highlights 2018-19
OUTLAY 2018-19 (Rupees in Crores)
1
|
New Lines
|
3631.29
|
2
|
Gauge Conversion
|
519.60
|
3
|
Doubling
|
1336.77
|
|
|
5487.66
|
EXPENDITURE 2018-19 (Rupees in Crores)
1
|
New Lines
|
3627.12
|
2
|
Gauge Conversion
|
567.45
|
3
|
Doubling
|
1333.39
|
|
|
5527.96
|
Mile Stones:
Commissioning
NEW LINES
|
GAUGE CONVERSION
|
DOUBLING
|
TOTAL
KM |
SN |
SECTION |
KM |
CRS Authorization Date |
SN |
SECTION |
KM |
CRS Authorization Date |
SN |
SECTION |
KM |
CRS Inspection Date |
1 |
Tetelia-Kamalazari |
10.15 |
25/10/2018 |
|
|
|
|
1 |
Hojai-Dholpukhuri-Lanka-Habaipur |
19.87 |
04/02/2019 |
|
2 |
Bogibeel Bridge Project - North Bank & South Bank Rail Link up to Bridge |
34.76 |
25/10/2018 |
|
|
|
|
2 |
Y leg connection Cabin-New Maynaguri |
5.72 |
30/03/2019 |
|
3 |
Santirbazar-Belonia |
10.00 |
03/12/2018 |
|
|
|
|
3 |
New Maynaguri-Betgara |
4.43 |
31/03/2019 |
|
4 |
Alamganj-Bilasipara |
26.14 |
30/03/2019 |
|
|
|
|
|
|
|
|
|
|
Total Length =
|
81.05 |
|
|
|
|
|
|
Total Length =
|
30.02 |
|
111.07 |
Engine Rolling (Flagging Off Of First Train)
NEW LINES
|
GAUGE CONVERSION
|
DOUBLING
|
TOTAL
KM |
SN |
SECTION |
KM |
Flagging Off Date |
SN |
SECTION |
KM |
Flagging Off Date |
SN |
SECTION |
KM |
Flagging Off Date |
1 |
North Bank-South Bank including Bogibeel Bridge(2 lines) |
48.70 |
25/12/2018 |
|
|
|
|
1 |
Hojai-Dholpukhuri-Lanka-Habaipur |
19.87 |
02/02/2019 |
|
|
Total Length =
|
48.70 |
|
|
|
|
|
|
Total Length = |
19.87 |
|
68.57 |