Achievement Highlights 2013-14
(Upto Match-2014)
OUTLAY 2013-14
|
|
|
|
|
|
|
|
|
1
|
New Lines
|
Rs.
|
1878.98
|
Crores
|
2
|
Gauge Conversion
|
Rs.
|
1606.65
|
Crores
|
3
|
Doubling
|
Rs.
|
104.75
|
Crores
|
4
|
Others
|
Rs.
|
6.45
|
Crores
|
|
|
Rs.
|
3596.83
|
Crores
|
|
|
|
|
|
|
|
|
|
|
EXPENDITURE 2013-14
|
|
|
|
|
|
|
|
|
1
|
New Lines
|
Rs.
|
1859.54
|
Crores
|
2
|
Gauge Conversion
|
Rs.
|
1614.55
|
Crores
|
3
|
Doubling
|
Rs.
|
103.25
|
Crores
|
4
|
Others
|
Rs.
|
6.63
|
Crores
|
|
|
Rs.
|
3583.97
|
Crores
|
Milestones :
Commissioning
NEW LINES
|
GAUGE CONVERSION
|
DOUBLING
|
Total
KM
|
SN
|
SECTION
|
KM
|
Date of CRS
Inspection
|
SN
|
SECTION
|
KM
|
Date of CRS
Inspection
|
SN
|
SECTION
|
KM
|
Date of CRS
Inspection
|
1
|
Harmuti-Naharlagun
|
22.00
|
29-03-14
|
1.
|
Rangiya-Rangapara North-Dekargaon
|
144.48
|
07-11-13
|
|
|
0
|
|
309.24
|
2.
|
Ranngapara North-Harmuti
|
142.76
|
28-03-14
|
|
Total length
|
22.00
|
|
|
|
287.24
|
|
|
|
0
|
|
|
Engine Rolling
NEW LINES
|
GAUGE CONVERSION
|
DOUBLING
|
Total
KM
|
SN
|
SECTION
|
KM
|
Date of CRS
Inspection
|
SN
|
SECTION
|
KM
|
Date of CRS
Inspection
|
SN
|
SECTION
|
KM
|
Date of CRS
Inspection
|
1.
|
Harmuti-Naharlagun (Balance Work)
|
2.00
|
14-01-14
|
1.
|
North Lakhimpur-Murkongselek of
|
154.00
|
30-03-14
|
1
|
Ambari Falakata- Belakoba
|
10.30
|
27-02-14
|
176.05
|
2.
|
Duodhnoi-Mendipathar (Balance Work)
|
9.75
|
31-03-14
|
2.
|
Rangiya - Murkongselek project
|
|
Total length
|
11.75
|
|
|
|
154.00
|
|
|
|
10.30
|
|
|
|